Namo Developers
Deedo IDDD-3RYVOf 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| MemoriesP52100001168 | Mohammadwadi | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Memories 90 - CommercialP52100013482 | Mohammadwadi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| MemoriesP52100016824 | Mohammadwadi | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| MemoriesP52100020409 | Mohammadwadi | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| MemoriesP52100023691 | Mohammadwadi | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Memories 90 - Phase IVP52100050004 | Mohammadwadi | Active | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Namo Developers, in questions
Does Namo Developers finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Namo Developers registered with MahaRERA?
4 projects under 6 MahaRERA registrations; 5 completed on MahaRERA.
Does Namo Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.