Nadeem Abdulrazak Bagwan
Deedo IDDD-BTXPOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 46 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hafiza HeightsP52100017454 | Pune (M Corp.) | Certificate Signed | 31 Dec 2021 | 30 Jun 2022 | +59 mo* |
| R K HeightsP52100047644 | Pune (M Corp.) | Certificate Signed | 31 Mar 2024 | 30 Sep 2025 | +32 mo* |
Nadeem Abdulrazak Bagwan, in questions
Does Nadeem Abdulrazak Bagwan finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 46 mo late. Across Maharashtra, 73% kept their date.
How many projects has Nadeem Abdulrazak Bagwan registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Nadeem Abdulrazak Bagwan have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.