Ms Ashar Realtors
Company or firm · 4 projects · 8 MahaRERA registrations
Projects48 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%7 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ashar Maple Phase 1 Building No.2P51700000969 | Thane (M Corp.) | 2017 | Not reported | 30 Dec 2022 | — | On date |
| AsharP51700000972 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| AsharP51700001081 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| AsharP51700001159 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| AsharP51700001169 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| AsharP51700001926 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Ashar Maple BirchP51800023941 | Kurla | 2020 | Not reported | 30 Dec 2025 | — | On date |
| Ashar TitanP51800045812 | Kurla | 2022 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 7 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Ashar Realtors (Suo Motu Case No. 4 of 2018) dated 8th Feb 2018 · Ashar Maple Phase 1 Building No.2 · P51700000969 · 8 Feb 2018
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology