Individual promoter · first RERA registration 2017

Mrunal Vivek Kanetkar

Deedo IDDD-E7MP

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 52 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay52 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sadanand SahaniwasP53100011561AshtaCertificate Signed31 Jul 202231 Jul 2022+52 mo*

Mrunal Vivek Kanetkar, in questions

Does Mrunal Vivek Kanetkar finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 52 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mrunal Vivek Kanetkar registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Mrunal Vivek Kanetkar have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology