Company or firm · first RERA registration 2018

Moze Associates

Deedo IDDD-F6P5

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.

Projects24 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay11 mowhen late · Maharashtra: 4 mo
First sales on record8registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Skyways EsferaP52100018101LohgaonCertificate Signed30 Oct 202230 Oct 2022On date
Skyways EsferaP52100018128LohgaonCertificate Signed30 Oct 202130 Oct 2021On date
Skyways EsferaP52100025786LohgaonCertificate Signed31 Oct 202230 Mar 2024+17 mo
Skyways Esfera C WingP52100034732LohgaonCertificate Signed31 Dec 202630 Apr 2027+4 mo

Moze Associates, in questions

Does Moze Associates finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Moze Associates registered with MahaRERA?

2 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.

Does Moze Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology