Morya Construction
Deedo IDDD-WN8FOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Morya ResidencyP52200015475 | Sangamner (Mcl) | Certificate Signed | 9 May 2019 | 9 May 2019 | +90 mo* |
| Morya GangaiP52200046982 | Sangamner (Mcl) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Morya Construction, in questions
Does Morya Construction finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Morya Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Morya Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.