Deedo IDDD-VT2COf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 20 mo late.
Delivery record
2 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Garden ViewP52100029162 | Chinchwad | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +35 mo* |
| GalaxyP52100049593 | Chinchwad | Certificate Signed | 31 May 2025 | 31 May 2025 | On date |
| Radhey Premlok Co Operative Housing Society LtdP52100054498 | Chinchwad | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| GurudeoP52100080077 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Akshay ResidencyPM1260002602616 | Chinchwad | Not on record | 31 Dec 2029 | — | On date |
Moraya Associates, in questions
Does Moraya Associates finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Moraya Associates registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Moraya Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.