Of 4 registrations whose promised date has arrived, 4 kept it (100%).

Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 4 registrations with dates has moved or missed its RERA date

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Eknath SadanP52000022440UlaweCertificate Signed30 Dec 202130 Dec 2021On date
Sunanda SadanP52000022540UlaweCertificate Signed30 Dec 202130 Dec 2021On date
Shree Ganesh NiwasP52000022897UlaweCertificate Signed28 Nov 202228 Nov 2022On date
Mahalaxmi NiwasP52000022904UlaweCertificate Signed28 Nov 202228 Nov 2022On date

Mmg Landmark Llp, in questions

Does Mmg Landmark Llp finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Mmg Landmark Llp registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Mmg Landmark Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology