Mind Space Realty Pvt. Ltd
Deedo IDDD-NMMVOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 64 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Msr OliveRegulatory order: PROJECT NAME: MSR OLIVE (Regulatory Case No. 311 OF 2024) dated 26 Dec 2024. | 26 Dec 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Msr SquareP52100004881 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Msr SeasonsP52100006114 | Chinchwad | Certificate Signed | 31 Dec 2019 | 31 Dec 2025 | +83 mo* |
| Msr OliveP52100008615 | Pune (M Corp.) | Certificate Signed | 30 Jun 2021 | 31 Mar 2025 | +45 mo |
Mind Space Realty Pvt. Ltd, in questions
Does Mind Space Realty Pvt. Ltd finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 64 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mind Space Realty Pvt. Ltd registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Mind Space Realty Pvt. Ltd have MahaRERA regulatory cases?
1 regulatory case name its registrations.