Mayureshwar Construction
Deedo IDDD-V6A3None of 2 registrations has reached its promised completion date yet.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mayureshwar PrideP52100055692 | Jalochi | Certificate Signed | 15 Apr 2027 | 15 Aug 2027 | +4 mo |
| Mayureshwar Classic APR1260002600184 | Jalochi | Certificate Signed | 20 Jan 2029 | 20 May 2029 | +4 mo |
Mayureshwar Construction, in questions
Does Mayureshwar Construction finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Mayureshwar Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Mayureshwar Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.