Mayur Group

Deedo IDDD-D584

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.

Projects44 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jagannath PrideP51700004903Badlapur (M Cl)Certificate Signed30 Mar 202230 Mar 2022On date
Jagannath GalaxyP51700018451Badlapur (M Cl)Certificate Signed30 Oct 202230 Dec 2024+26 mo
Jagannath ParadiseP51700050635AmbarnathCertificate Signed30 Sep 202630 Sep 2026+2 mo*
Jyoti Jagannath HeritagePM1330002501384Badlapur (M Cl)Certificate Signed31 Dec 202930 Apr 2030+4 mo

Mayur Group, in questions

Does Mayur Group finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mayur Group registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Mayur Group have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology