Matrix Enclaves Projects Dev. Pvt. Ltd
Company or firm · 3 projects · 5 MahaRERA registrations
3Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
20%Kept RERA date1 of 5 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Marathon Nexworld ElaraP51700000470 | Thane (M Corp.) | 2017 | Not reported | 30 Dec 2024 | — | On date |
| Marathon Nexworld ElaraP51700000478 | Thane (M Corp.) | 2017 | Not reported | 30 Jun 2023 | 29 Jun 2024 | +12 months |
| Marathon Nexworld AuraP51700000507 | Thane (M Corp.) | 2017 | Not reported | 30 Jun 2023 | 29 Jun 2024 | +12 months |
| Marathon Nexworld AuraP51700000652 | Thane (M Corp.) | 2017 | Not reported | 30 Dec 2022 | 29 Dec 2023 | +12 months |
| Marathon Nexworld Aura-3P51700022847 | Thane (M Corp.) | 2019 | Not reported | 30 Dec 2024 | 31 Dec 2026 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Marathon Nexworld Aura-3 (P51700022847).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology