Individual promoter · 3 projects · 3 MahaRERA registrations
Also appears as MARUTI SAYABANNA Mehetre
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai VrindavanP52100008093 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Sai AanganP52100020698 | Pimpri Chinchawad (M Corp.) | 2019 | Not reported | 30 Dec 2023 | — | On date |
| Renuka NilayP52100030696 | Moshi | 2021 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology