Marimagnum Constructions
Deedo IDDD-X0T7Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 37 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mi CasaP52100009650 | Undri | Certificate Signed | 31 Mar 2020 | 25 Sep 2024 | +54 mo |
| TheCrownP52100034902 | Undri | Certificate Signed | 31 Mar 2025 | 30 Sep 2025 | +20 mo* |
Marimagnum Constructions, in questions
Does Marimagnum Constructions finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 37 mo late. Across Maharashtra, 73% kept their date.
How many projects has Marimagnum Constructions registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Marimagnum Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.