Manoj Dilip Sakarkar

Deedo IDDD-31H6

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay15 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vrushank ParkP50100023804Akola (M Corp.)Completed1 Oct 20211 Jan 2023+15 mo

Manoj Dilip Sakarkar, in questions

Does Manoj Dilip Sakarkar finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.

How many projects has Manoj Dilip Sakarkar registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Manoj Dilip Sakarkar have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.