Mangal Buildhome Private Limited

Company or firm · 6 projects · 6 MahaRERA registrations

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree MangalP51800004380Andheri2017Not reported31 Dec 2017—On date
AmrapaliP51800015180Andheri2018Certificate Signed30 Dec 202130 Dec 2021On date
RoyaleP51800045406Andheri2022Not reported31 May 2025—On date
Mangal Business Park - Gautam ApartmentP51800054656Malad2024Not reported31 Mar 2027—On date
SignatureP51800078445Vileparle2024Not reported31 Mar 2028—On date
Aarya By MangalPR1180002600023Juhu2026Not reported31 Mar 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree MangalOn date
  • AmrapaliOn date
  • RoyaleOn date
  • Mangal Business Park - Gautam ApartmentOn date
  • SignatureOn date
  • Aarya By MangalOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology