Manali & Company

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+25 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shreeji Tower ResidentialP51500003486Aurangabad (M Corp.)2017Lapsed3 Jul 201930 Sep 2023+50 months
Shreeji Tower Phase IIP51500049749Aurangabad (M Corp.)2023Not reported30 Sep 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shreeji Tower Residential+50 mo
  • Shreeji Tower Phase IIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 50 months, for Shreeji Tower Residential (P51500003486).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology