Mali Infra
Deedo IDDD-ERAGOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mali PinnacleP51700026067 | Bhal | Certificate Signed | 31 Jan 2025 | 31 Jan 2027 | +24 mo |
| Mali AvenueP51700055096 | Bhal | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Mali ShivalayaPM1330002602683 | Dombivli | Not on record | 31 Aug 2029 | — | On date |
Mali Infra, in questions
Does Mali Infra finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mali Infra registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Mali Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.