Deedo IDDD-WVQCOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 96 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Maitri PrasadP51700003086 | Dombivli | Certificate Signed | 21 Nov 2018 | 21 Nov 2018 | On date |
| Maitri Indira SadanP51700003973 | Dombivli | Certificate Signed | 21 Nov 2018 | 21 Nov 2018 | +96 mo* |
Maitri Construction, in questions
Does Maitri Construction finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 96 mo late. Across Maharashtra, 73% kept their date.
How many projects has Maitri Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Maitri Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.