Mahesh Shankarrao Gulhane
Deedo IDDD-ZGSKOf 11 registrations whose promised date has arrived, 10 kept it (91%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 11 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 11 registrations
11 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aai nagariP50400023816 | Sindi Turf Hindnagar (Ct) | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Aai Krupa NagariP50400028833 | Sindi Turf Hindnagar (Ct) | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Shri Baba Aashirwad NagariP50400030817 | Sindi Turf Hindnagar (Ct) | Completed | 31 Mar 2023 | — | On date |
| Shankar NagarP50400033161 | Masala (Ct) | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| baramati cityP50400033991 | Hinganghat | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Baramati CityP50400033992 | Hinganghat | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Baramati CityP50400033993 | Hinganghat | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Ayodhya City-Residential Layout Plan in Survey No-107/2P50400048190 | Umari (Meghe) | Active | 31 Mar 2024 | 31 Mar 2027 | +36 mo |
| Gurukrupa Nagari - Residential Layout Plan in Survey No.66/4/1KP50400048459 | Pipri (Ct) | Completed | 31 Mar 2024 | — | On date |
| Mahalaxmi City Residential Layout Plan In Survey No 128 129 108/1P50400048502 | Masala (Ct) | Completed | 31 Mar 2024 | — | On date |
| Sai Dham CityP50500056089 | Narsala (Ri) | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
Show all 11 registrationsShow fewer
Mahesh Shankarrao Gulhane, in questions
Does Mahesh Shankarrao Gulhane finish projects on time?
Of 11 MahaRERA registrations whose promised completion date has arrived, 10 kept it (91%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mahesh Shankarrao Gulhane registered with MahaRERA?
11 projects under 11 MahaRERA registrations; 10 completed on MahaRERA.
Does Mahesh Shankarrao Gulhane have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.