M/S.Five Star Shelters

Deedo IDDD-0E4C

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 27 mo late.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay27 mowhen late
First sales on record1registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Royal RadianceP52100022253RahataniCertificate Signed30 Mar 202130 Mar 2021On date
ANP - ATLANTIS -Phase IP52100024229BanerCertificate Signed30 Dec 202530 Dec 2025On date
Anp OlympusP52100051936BalewadiCertificate Signed31 Aug 202431 Aug 2024+27 mo*

M/S.Five Star Shelters, in questions

Does M/S.Five Star Shelters finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 27 mo late. Across Maharashtra, 73% kept their date.

How many projects has M/S.Five Star Shelters registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does M/S.Five Star Shelters have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology