Deedo IDDD-0E4COf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 27 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Royal RadianceP52100022253 | Rahatani | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| ANP - ATLANTIS -Phase IP52100024229 | Baner | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Anp OlympusP52100051936 | Balewadi | Certificate Signed | 31 Aug 2024 | 31 Aug 2024 | +27 mo* |
M/S.Five Star Shelters, in questions
Does M/S.Five Star Shelters finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 27 mo late. Across Maharashtra, 73% kept their date.
How many projects has M/S.Five Star Shelters registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does M/S.Five Star Shelters have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.