Company or firm · first RERA registration 2017

Luxora Infrastructure Private Limited

Deedo IDDD-DTM8

Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 39 mo late — longer than Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay39 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Treeline 5P50500002936PiplaCertificate Signed31 Dec 201930 Dec 2021+24 mo
Vista 3CP50500007884PiplaCertificate Signed31 Dec 201930 Jun 2024+54 mo
The MeadowsP50500013138PiplaCertificate Signed30 Sep 201930 Sep 2019On date
The WillowsP50500014261PiplaCertificate Signed30 Sep 201930 Sep 2019On date

Luxora Infrastructure Private Limited, in questions

Does Luxora Infrastructure Private Limited finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 39 mo late. Across Maharashtra, 73% kept their date.

How many projects has Luxora Infrastructure Private Limited registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Luxora Infrastructure Private Limited have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology