Luxora Infrastructure Private Limited
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Treeline 5P50500002936 | Pipla | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Vista 3CP50500007884 | Pipla | 2017 | Not reported | 31 Dec 2019 | 30 Jun 2024 | +54 months |
| The MeadowsP50500013138 | Pipla | 2017 | Not reported | 30 Sep 2019 | — | On date |
| The WillowsP50500014261 | Pipla | 2017 | Not reported | 30 Sep 2019 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 54 months, for Vista 3C (P50500007884).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:VISTA 3C (Regulatory Case No.89 of 2023) dated 7 November 2023. · Vista 3C · P50500007884 · 7 Nov 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology