Luxora Infrastructure Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Treeline 5P50500002936Pipla2017Not reported31 Dec 201930 Dec 2021+24 months
Vista 3CP50500007884Pipla2017Not reported31 Dec 201930 Jun 2024+54 months
The MeadowsP50500013138Pipla2017Not reported30 Sep 2019—On date
The WillowsP50500014261Pipla2017Not reported30 Sep 2019—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Treeline 5+24 mo
  • Vista 3C+54 mo
  • The MeadowsOn date
  • The WillowsOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Vista 3C (P50500007884).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology