Company or firm · first RERA registration 2018
Lodha Developers Limited
Deedo IDDD-VS9CNone of 13 registrations has reached its promised completion date yet.
Projects1113 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
8 of 13 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 13 registrations
13 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Bellissimo Mulund T2Regulatory order: PROJECT NAME: BELLISSIMO MULUND T2 (Regulatory Case No. 389 OF 2025) dated 17 July, 2025. | 17 Jul 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bellissimo Mulund T2P51800018893 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Lodha BellagioP51800033966 | Kurla | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Lodha BellagioP51800034759 | Kurla | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Acenza Tower A and BP51800048862 | Andheri | Certificate Signed | 31 May 2027 | 31 May 2027 | On date |
| AcenzaP51800052417 | Gundavali | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Vikhroli ASPI ProjectP51800053072 | Vikhroli | Active | 30 Sep 2028 | — | On date |
| CullinanP51800054551 | Varsova | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Alibaug ProjectP52000078155 | Dhokawade | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
| Alibaug TownhousesP52000078856 | Alibag | Certificate Signed | 31 Aug 2029 | 31 Dec 2029 | +4 mo |
| Alibaug Residential ProjectP52000079314 | Dhokawade | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Alibaug PlotsP52000079427 | Dhokawade | Certificate Signed | 31 Aug 2029 | 31 Dec 2029 | +4 mo |
| Hinjewadi Premium - Tower 10PR1260002502009 | Hinjavadi (Ct) | Certificate Signed | 31 Jul 2032 | 30 Nov 2032 | +4 mo |
| AcenzaPR1180002600659 | Gundavali | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Show all 13 registrationsShow fewer
Lodha Developers Limited, in questions
Does Lodha Developers Limited finish projects on time?
None of its 13 MahaRERA registrations has reached its promised completion date yet.
How many projects has Lodha Developers Limited registered with MahaRERA?
11 projects under 13 MahaRERA registrations; 2 completed on MahaRERA.
Does Lodha Developers Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology