Linux Group

Deedo IDDD-3QDR

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 29 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay29 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
VientoP52100023329SusCertificate Signed30 Dec 202230 Dec 2022+47 mo*
BonheurP52100026648WakadCertificate Signed30 Jun 202430 Jun 2024+29 mo*
iOS TathawadeP52100027952TathwadeCertificate Signed10 Jul 202430 Dec 2024+5 mo

Linux Group, in questions

Does Linux Group finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.

How many projects has Linux Group registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Linux Group have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology