Linux Group
Deedo IDDD-JBX6Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 6 mo late.
Delivery record
6 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VientoP52100023329 | Sus | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
| BonheurP52100026648 | Wakad | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| iOS TathawadeP52100027952 | Tathwade | Certificate Signed | 10 Jul 2024 | 30 Dec 2024 | +5 mo |
| Bonheur A wingP52100032282 | Wakad | Certificate Signed | 30 Apr 2026 | 30 Aug 2026 | +7 mo* |
| Ios PrimeP52100053819 | Tathwade | Certificate Signed | 30 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ios Prime B1P52100079123 | Tathwade | Certificate Signed | 30 Dec 2029 | 30 Apr 2030 | +4 mo |
Linux Group, in questions
Does Linux Group finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Linux Group registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Linux Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.