Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date60%3 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Maryam HeightP51700017434Kalyandombivali (M Corp.)2018Not reported30 Dec 2023—On date
Rabiya HeightP51700017593Kalyandombivali (M Corp.)2018Not reported30 Dec 2023—On date
Laiba HeightsP51700032899Kalyandombivali (M Corp.)2022Not reported30 Jun 202431 Dec 2027+42 months
Fatima HeightsP51700032965Kalyan-Dombivali (M Corp.)2022Not reported30 Jun 202430 Jun 2025+12 months
Lucky HeightP51700050303Kalyandombivali (M Corp.)2023Not reported31 Dec 2025—On date
Fatima SkyP51700054322Kalyandombivali (M Corp.)2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Maryam HeightOn date
  • Rabiya HeightOn date
  • Laiba Heights+42 mo
  • Fatima Heights+12 mo
  • Lucky HeightOn date
  • Fatima SkyOn date

Track record notes

  • 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Laiba Heights (P51700032899).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.