Deedo IDDD-1MQ1Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
2 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Legacy AuraP52100000710 | Rahatani | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Legacy VistaP52100024212 | Rahatani | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Legacy IvyP52100029412 | Punawale | Certificate Signed | 31 Jul 2024 | 31 Jul 2024 | On date |
| Legacy CelestiaP52100030612 | Wakad | Certificate Signed | 1 Sep 2024 | 1 Sep 2024 | On date |
| Legacy KairosP52100047901 | Rahatani | Certificate Signed | 30 Mar 2028 | 30 Jul 2028 | +4 mo |
| Legacy KairosP52100047999 | Rahatani | Certificate Signed | 30 Mar 2027 | 30 Mar 2027 | On date |
| Legacy EkamPM1260002502297 | Punawale | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Legacy Lifespaces Llp, in questions
Does Legacy Lifespaces Llp finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Legacy Lifespaces Llp registered with MahaRERA?
6 projects under 7 MahaRERA registrations; 5 completed on MahaRERA.
Does Legacy Lifespaces Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.