Laukik Construction Company

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pelican Phase BP52100000949Ambadvet2017Not reported31 Dec 201930 Dec 2022+36 months
Pelican Phase CP52100033925Ambadvet2022Not reported28 Feb 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pelican Phase B+36 mo
  • Pelican Phase COn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Pelican Phase B (P52100000949).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology