Individual promoter · first RERA registration 2021

Lakshman Daulat Mali

Deedo IDDD-YD4A

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Laxman AvenueP49900029456Chopda (M Cl)Lapsed30 Apr 2022—+55 mo*

Lakshman Daulat Mali, in questions

Does Lakshman Daulat Mali finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 55 mo late. Across Maharashtra, 73% kept their date.

How many projects has Lakshman Daulat Mali registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Lakshman Daulat Mali have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology