Kukreja Infrastructures
Company or firm · 8 projects · 8 MahaRERA registrations · 1 reported completed
8Projects8 RERA registrations
1Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Suncity 2P50500005011 | Nagpur (M Corp.) | 2017 | Not reported | 29 Dec 2021 | — | On date |
| Kukreja InfinityP50500015438 | Nagpur (M Corp.) | 2018 | Completed | 30 Dec 2023 | — | On date |
| Kukreja Business ParkP50500029443 | Dahegaon | 2021 | Not reported | 31 Mar 2025 | 31 Mar 2029 | +48 months |
| Kukreja Infinity EastP50500030914 | Nagpur (M Corp.) | 2021 | Not reported | 30 Nov 2026 | — | On date |
| Kukreja Paris City-Wing C & DP50500049636 | Nagpur (Urban) | 2023 | Not reported | 31 Dec 2029 | — | On date |
| The OneP50500052313 | Nagpur (Urban) | 2023 | Not reported | 31 Dec 2029 | — | On date |
| Kukreja Embassy-IIP50500076706 | Nagpur (M Corp.) | 2024 | Active | 30 Nov 2028 | — | On date |
| Kukreja Paris City Wing-A, B, E And FP50500076938 | Nagpur (M Corp.) | 2024 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 48 months, for Kukreja Business Park (P50500029443).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: KUKREJA BUSINESS PARK (Regulatory Case No. 377 OF 2025) dated 18 June, 2025. · Kukreja Business Park · P50500029443 · 18 Jun 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology