Kuber Properties
Deedo IDDD-YCQKNone of 3 registrations has reached its promised completion date yet.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kuber Properties Kuber Antonia BPR1260002501797 | Wakad | Certificate Signed | 24 Apr 2027 | 24 Aug 2027 | +4 mo |
| The Vantage EPC1260002600820 | Wakad | Certificate Signed | 19 Mar 2031 | 19 Jul 2031 | +4 mo |
| The Vantage A, B, C & DPR1260002601066 | Wakad | Certificate Signed | 19 Mar 2031 | 19 Jul 2031 | +4 mo |
Kuber Properties, in questions
Does Kuber Properties finish projects on time?
None of its 3 MahaRERA registrations has reached its promised completion date yet.
How many projects has Kuber Properties registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Kuber Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.