Krishna Enterprises Builders & Developers

Deedo IDDD-CCWZ

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 20 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay20 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Krishna ResidencyP52000022634VichumbeCertificate Signed30 Dec 202330 Dec 2023+35 mo*
Krishna PalaceP52000046628VichumbeCertificate Signed31 Dec 202630 Apr 2027+4 mo

Krishna Enterprises Builders & Developers, in questions

Does Krishna Enterprises Builders & Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.

How many projects has Krishna Enterprises Builders & Developers registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Krishna Enterprises Builders & Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology