Deedo IDDD-R2GNOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Krishna DarshanP51700049959 | Badlapur (M Cl) | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 mo |
| Akanksha Co. Op. Hsg. Soc. Ltd.P51700076666 | Kulgaon | Active | 31 Dec 2026 | — | On date |
| Vishnu Krupa Co operative Housing SocietyPM1330002601125 | Kulgaon | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Krishna Buildcon, in questions
Does Krishna Buildcon finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Krishna Buildcon registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Krishna Buildcon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.