RegisteredExtendedMahaRERA status: Certificate Signed

PM1330002601125

Vishnu Krupa Co operative Housing Society · Kulgaon, Thane · Krishna Buildcon

Promised for 31 Dec 2029, extended to 30 Apr 2030, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2029 to 30 Apr 2030.

Documents 1

Registration certificate9 Jul 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PM1330002601125

Is Vishnu Krupa Co operative Housing Society delayed?

Its completion moved from 31 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PM1330002601125. The completion date moved from 31 Dec 2029 to 30 Apr 2030.

Who is the promoter?

MahaRERA records Krishna Buildcon as the promoter of PM1330002601125.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PM1330002601125.