Konark Lifespaces
Deedo IDDD-C383Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aryan OneP51700002130 | Shirgaon | Certificate Signed | 31 Jul 2018 | 31 Jul 2019 | +12 mo |
| Aryan One Wing E And FP51700009247 | Shirgaon | Certificate Signed | 30 Apr 2018 | 31 Mar 2019 | +11 mo |
| Aryan OneP51700015793 | Shirgaon | Certificate Signed | 31 Oct 2018 | 31 Oct 2018 | On date |
Konark Lifespaces, in questions
Does Konark Lifespaces finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Konark Lifespaces registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Konark Lifespaces have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.