Konark Lifespaces

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+11 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aryan OneP51700002130Ambarnath2017Not reported31 Jul 201831 Jul 2019+12 months
Aryan One Wing E And FP51700009247Ambarnath2017Not reported30 Apr 201831 Mar 2019+11 months
Aryan OneP51700015793Ambarnath2018Not reported31 Oct 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aryan One+12 mo
  • Aryan One Wing E And F+11 mo
  • Aryan OneOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Aryan One (P51700002130).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology