KoltePatil IVen Townships (Pune) Limited
Deedo IDDD-WAJFOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Life Republic Sector R2 - 2nd AvenueP52100002682 | Marunji | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Life Republic Sector R3 3rd AvenueP52100007511 | Jambe | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
KoltePatil IVen Townships (Pune) Limited, in questions
Does KoltePatil IVen Townships (Pune) Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has KoltePatil IVen Townships (Pune) Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does KoltePatil IVen Townships (Pune) Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.