Company or firm · first RERA registration 2020

Knight West Realty Llp

Deedo IDDD-QFR3

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Espacio - A And BP52100025098BalewadiCertificate Signed30 Dec 202630 Apr 2027+4 mo
Espacio - Wing C D And E/MHADAP52100025099BalewadiCertificate Signed30 Dec 202530 Dec 2025On date
Espacio - CommercialP52100026492BalewadiCertificate Signed30 Jun 202530 Jun 2025On date
ArvaanaPR1260002600277BalewadiCertificate Signed31 Dec 203030 Apr 2031+4 mo

Knight West Realty Llp, in questions

Does Knight West Realty Llp finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Knight West Realty Llp registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Knight West Realty Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology