Km Developers

Deedo IDDD-F1H3

None of 4 registrations has reached its promised completion date yet.

Projects24 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Horizon PalmsP51700028504OwaleCertificate Signed31 Dec 202631 Dec 2026On date
Horizon PearlP51700050797OwaleCertificate Signed30 Apr 202730 Aug 2027+4 mo
Horizon PalmsPM1330002400089OwaleCertificate Signed31 Dec 202730 Apr 2028+4 mo
Horizon PearlP51700079782OwaleCertificate Signed31 Dec 202830 Apr 2029+4 mo

Km Developers, in questions

Does Km Developers finish projects on time?

None of its 4 MahaRERA registrations has reached its promised completion date yet.

How many projects has Km Developers registered with MahaRERA?

2 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.

Does Km Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology