Company or firm · first RERA registration 2017

Kesar Vighnaharta Group

Deedo IDDD-ZGR3

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 20 mo late.

Projects23 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay20 mowhen late
First sales on record17registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kesar Tree TownP52100006616MoshiCertificate Signed30 Dec 202030 Dec 2020On date
Kesar TreetownP52100021258MoshiCertificate Signed30 Dec 202330 Dec 2023+35 mo*
Kesar TreetownP52100045320MoshiCertificate Signed31 Dec 202630 Apr 2027+4 mo

Kesar Vighnaharta Group, in questions

Does Kesar Vighnaharta Group finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kesar Vighnaharta Group registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Kesar Vighnaharta Group have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology