Kedar Buildcon

Deedo IDDD-GJ1M

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SunflowerP52000045642PanvelCertificate Signed31 Mar 202631 Mar 2026On date
Yashomangal C.h.s.P52000078290PanvelCertificate Signed30 Sep 202830 Jan 2029+4 mo

Kedar Buildcon, in questions

Does Kedar Buildcon finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Kedar Buildcon registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Kedar Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology