Kasim Mohamed Maner
Deedo IDDD-SJFSOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 16 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Khushi PrideP53100028957 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 30 May 2024 | 30 May 2024 | On date |
| Khushi IconicP53100047975 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 9 Jul 2025 | 9 Jul 2025 | +16 mo* |
Kasim Mohamed Maner, in questions
Does Kasim Mohamed Maner finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 16 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kasim Mohamed Maner registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Kasim Mohamed Maner have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.