Karda Constructions Limited
Deedo IDDD-2T2ROf 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 83 mo late.
Delivery record
1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hari Sparsh IIP51600000119 | Bhagur Rural | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Hari VatikaP51600000220 | Sansari | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Hari Sparsh Phase IIIP51600000225 | Bhagur Rural | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Hari Vishwa D BuildingP51600001205 | Nashik | Certificate Signed | 31 Dec 2019 | 31 Aug 2023 | +83 mo* |
Karda Constructions Limited, in questions
Does Karda Constructions Limited finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 83 mo late. Across Maharashtra, 73% kept their date.
How many projects has Karda Constructions Limited registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Karda Constructions Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.