Karan Kothari Business Park Private Limited

Deedo IDDD-DQYM

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Karan Kothari Business Park Shopping VillageP50500055653WanjaraCertificate Signed15 Oct 202715 Feb 2028+4 mo

Karan Kothari Business Park Private Limited, in questions

Does Karan Kothari Business Park Private Limited finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Karan Kothari Business Park Private Limited registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Karan Kothari Business Park Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.