Company or firm · first RERA registration 2022

Kanika Infracon Llp

Deedo IDDD-SH3M

None of 4 registrations has reached its promised completion date yet.

Projects34 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record178registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The Balmoral HillsideP52100046444BanerCertificate Signed31 Dec 202830 Apr 2029+4 mo
The Balmoral HillsideP52100052022BanerCertificate Signed30 Jun 202930 Oct 2029+4 mo
Habitat-Wing CPR1260002500609BanerCertificate Signed31 Dec 202730 Apr 2028+4 mo
The Balmoral Hillside - CommercialPC1260002501179BanerCertificate Signed30 Jun 202930 Oct 2029+4 mo

Kanika Infracon Llp, in questions

Does Kanika Infracon Llp finish projects on time?

None of its 4 MahaRERA registrations has reached its promised completion date yet.

How many projects has Kanika Infracon Llp registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.

Does Kanika Infracon Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology