Kanika Infracon Llp
Deedo IDDD-SH3MNone of 4 registrations has reached its promised completion date yet.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| The Balmoral HillsideP52100046444 | Baner | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| The Balmoral HillsideP52100052022 | Baner | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| Habitat-Wing CPR1260002500609 | Baner | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| The Balmoral Hillside - CommercialPC1260002501179 | Baner | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
Kanika Infracon Llp, in questions
Does Kanika Infracon Llp finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Kanika Infracon Llp registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Kanika Infracon Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.