Kalpataru Limited

Company or firm · 8 projects · 10 MahaRERA registrations

8Projects10 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kalpataru SolitaireP51800000699Andheri2017Not reported31 Dec 2019—On date
Kalpataru AvanaP51900000793Ward Fsouth2017Not reported30 Dec 2022—On date
Matru AshishP51900019426Mumbai City2019Not reported30 Dec 202329 Dec 2024+12 months
Kalpataru ImperiaP51800020203Andheri2019Not reported30 Jun 2024—On date
Kalpataru AmareP51800056013Andheri2024Not reported31 Dec 2027—On date
Kalpataru AdvayP51800077381Eksar2024Not reported30 Jun 2030—On date
Kalpataru BlossomsP52100077649Wadgaon Bk2024Not reported31 Mar 2029—On date
Kalpataru BlossomsP52100077659Wadgaon Bk2024Not reported31 Mar 2029—On date
Kalpataru Blossoms - Inclusive HousingP52100077715Wadgaon Bk2024Not reported31 Mar 2029—On date
Kalpataru BlossomsP52100077750Wadgaon Bk2024Not reported31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kalpataru SolitaireOn date
  • Kalpataru AvanaOn date
  • Matru Ashish+12 mo
  • Kalpataru ImperiaOn date
  • Kalpataru AmareOn date
  • Kalpataru AdvayOn date
  • Kalpataru BlossomsOn date
  • Kalpataru BlossomsOn date
  • Kalpataru Blossoms - Inclusive HousingOn date
  • Kalpataru BlossomsOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Matru Ashish (P51900019426).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology