Kalbhor Realtors And Services Llp
Deedo IDDD-S9KEOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gaatha Nagar Phase 1P52100046021 | Chikhali | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | +32 mo* |
| Vaishnav GaathaP52100052318 | Chikhali | Certificate Signed | 30 Jun 2025 | 31 Dec 2026 | +18 mo |
Kalbhor Realtors And Services Llp, in questions
Does Kalbhor Realtors And Services Llp finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 25 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kalbhor Realtors And Services Llp registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Kalbhor Realtors And Services Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.