Kabra And Associates

Company or firm · 8 projects · 8 MahaRERA registrations

Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%6 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
KABRA CENTROID A Redevelopment of GOP CHSLP51800000307Andheri2017Not reported30 Dec 2021—On date
KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSLP51800001067Andheri2017Not reported30 Dec 2022—On date
KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society LtdP51800002483Andheri2017Not reported30 Dec 2021—On date
KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSLP51800005550Andheri2017Not reported31 Dec 2019—On date
TILAK Revelopment Project of TILAK APARTMENT CHSLP51800007990Andheri2017Not reported31 Dec 2017—On date
Kabra DiamanteP51800030391Borivali2021Not reported31 Dec 2025—On date
KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc LtdP51800051344Malad2023Not reported31 Dec 2026—On date
KABRA TIARA - Redevelopment of Dindoshi Darshan CHSLP51800054840Dindoshi2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • KABRA CENTROID A Redevelopment of GOP CHSLOn date
  • KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSLOn date
  • KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society LtdOn date
  • KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSLOn date
  • TILAK Revelopment Project of TILAK APARTMENT CHSLOn date
  • Kabra DiamanteOn date
  • KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc LtdOn date
  • KABRA TIARA - Redevelopment of Dindoshi Darshan CHSLOn date

Track record notes

  • 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology