Kabra And Associates
Company or firm · 8 projects · 8 MahaRERA registrations
Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%6 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| KABRA CENTROID A Redevelopment of GOP CHSLP51800000307 | Andheri | 2017 | Not reported | 30 Dec 2021 | — | On date |
| KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSLP51800001067 | Andheri | 2017 | Not reported | 30 Dec 2022 | — | On date |
| KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society LtdP51800002483 | Andheri | 2017 | Not reported | 30 Dec 2021 | — | On date |
| KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSLP51800005550 | Andheri | 2017 | Not reported | 31 Dec 2019 | — | On date |
| TILAK Revelopment Project of TILAK APARTMENT CHSLP51800007990 | Andheri | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Kabra DiamanteP51800030391 | Borivali | 2021 | Not reported | 31 Dec 2025 | — | On date |
| KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc LtdP51800051344 | Malad | 2023 | Not reported | 31 Dec 2026 | — | On date |
| KABRA TIARA - Redevelopment of Dindoshi Darshan CHSLP51800054840 | Dindoshi | 2024 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Ms Kabra & Associates Pvt. Ltd. (Suo Motu Case No. 7 of 2018) dated 8th Feb 2018 · KABRA CENTROID A Redevelopment of GOP CHSL · P51800000307 · 8 Feb 2018
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Ms Kabra & Associates Pvt. Ltd. (Suo Motu Case No. 7 of 2018) dated 8th Feb 2018 · KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society Ltd · P51800002483 · 8 Feb 2018
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology