K B D Realty
Deedo IDDD-926WOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 29 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Prospera Palms OrnamentP52100026101 | Katavi | Certificate Signed | 15 Jun 2023 | 15 Jun 2023 | On date |
| Prospera Palms PearlP52100026249 | Katavi | Certificate Signed | 15 Jun 2023 | 15 Jun 2023 | +41 mo* |
| Prospera ParadiseP52100048291 | Katavi | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Prospera ParadiseP52100048317 | Katavi | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
K B D Realty, in questions
Does K B D Realty finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.
How many projects has K B D Realty registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does K B D Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.