Jagrut Sara Associates
Deedo IDDD-8MQ2Of 5 registrations whose promised date has arrived, 5 kept it (100%).
Delivery record
None of 6 registrations with dates has moved or missed its RERA date
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sara Sangam Phase 1P51500016384 | Wadgaon Kolhati (Ct) | Completed | 30 Dec 2021 | — | On date |
| Sara Sangam Panchganga BuildingP51500024081 | Wadgaon Kolhati (Ct) | Certificate Signed | 30 May 2022 | 30 May 2022 | On date |
| Sara Sangam Plot 1P51500024165 | Wadgaon Kolhati (Ct) | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Sara Sangam Ganga BldgP51500030505 | Wadgaon Kolhati (Ct) | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Sara Sangam - Narmada And Sharayu BuildingP51500045949 | Wadgaon Kolhati (Ct) | Completed | 31 Mar 2025 | — | On date |
| Sara Sangam Kaveri BuildingP51500053231 | Wadgaon Kh. | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
Jagrut Sara Associates, in questions
Does Jagrut Sara Associates finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 5 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Jagrut Sara Associates registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 6 completed on MahaRERA.
Does Jagrut Sara Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.