Jagrut Sara Associates
Company or firm · 6 projects · 6 MahaRERA registrations · 2 reported completed
Projects66 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sara Sangam Phase 1P51500016384 | Wadgaon Kolhati (Ct) | 2018 | Completed | 30 Dec 2021 | — | On date |
| Sara Sangam Panchganga BuildingP51500024081 | Wadgaon Kolhati (Ct) | 2020 | Not reported | 30 May 2022 | — | On date |
| Sara Sangam Plot 1P51500024165 | Wadgaon Kolhati (Ct) | 2020 | Not reported | 30 Dec 2025 | — | On date |
| Sara Sangam Ganga BldgP51500030505 | Wadgaon Kolhati (Ct) | 2021 | Not reported | 31 Mar 2024 | — | On date |
| Sara Sangam - Narmada And Sharayu BuildingP51500045949 | Wadgaon Kolhati (Ct) | 2022 | Completed | 31 Mar 2025 | — | On date |
| Sara Sangam Kaveri BuildingP51500053231 | Wadgaon Kh. | 2023 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology