Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
VivaP52100001673Hinjavadi (Ct)Certificate Signed31 Jul 201831 Jul 2018On date
Icon Business SpacesP52100049148BanerCertificate Signed31 Aug 202531 Aug 2025On date
ShantiniketanPR1260002502400Shukrawar PethCertificate Signed31 Dec 202830 Apr 2029+4 mo
VishnupadPR1260002602385Shukrawar PethNot on record1 Jun 2029—On date

Icon Realty, in questions

Does Icon Realty finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Icon Realty registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Icon Realty have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.